North Bridle Creek
South Bridle Creek Gravity Sewer Outfall
|
Public Works Commission of the City of Fayetteville
M. J. Noland, PE (910) 223-4733
|
$2,861,000 |
The combined project included 13,185 feet of 15”, 2,622 feet of 12” and 8,930 feet of 8” (approximately 4.7 miles) of sewer outfall. An environmental assessment permit was required. The entire project to include EA permit, engineering and construction was completed in 22 months (“start to finish”), saving PWC approximately $150,000 by eliminating a proposed temporary lift station. One of the 1st projects to use “Pipe Ramming” to cross under US 401 due to extremely wet soil conditions and NCDOT well point restrictions. Included a bore thru a dam and substantial construction in wetlands. Responsibilities included EA permitting, wetland permitting, route surveying, engineering, easement maps and descriptions, encroachment permitting, project administration, full time construction observation and construction staking. |
|